Project History

This page will provide a brief history of the project to-date.

*Click the underlined text for links.

2023 Summary

In 2023, a pre-design public outreach phase was conducted. This initial public outreach helped shape the direction of the project.

June 2023

City Council Study Session

June 2023 - November 2023

Public Survey Period

September/October 2023

Two Open House Community Meetings

December 2023:

City Council Study Session

2024 Summary

In 2024, the project scope was finalized. Kimley-Horn was awarded the Engineering Design Services Contract and initial design began.

February 2024

Scoping Report Finalized

March 2024 - July 2024

Request for Statement of Qualifications

November 19, 2024

Award Engineering Design Services Contract

2025 Summary

2025 consisted of hosting the Technical Advisory Committee meetings, developing the Design Ranking Criteria, and completing the three Design Concepts, Traffic Impact Analysis and Public Comment Period. Following the completion of these items, City Council directed the project team to move forward with Design Option 2C.

April 8, 2025

City Council Study Session

July 8, 2025

City Council Study Session (1 of 2)

Traffic Impact Analysis Completed

Public Comment Period opens

August 26, 2025

City Council Study Session (2 of 2) and Public Hearing (1 of 2)

October 1, 2025

Open House Meeting

October 9, 2025

Close of Public Comment Period

October 14, 2025

Public Hearing (2 of 2)

November 2025

Design Concept Report Complete

2026 Summary

2026 has consisted of our project team working on designing Design Option 2C.

April 25, 2025

City Council Voting Session

At the August 25 Council meeting the public asked questions about the responsibilities of the design team versus the construction manager at risk (CMAR) providing pre-construction services.  The following table lists the public’s questions and the difference in services provided by the design team and CMAR.  Additional information was provided at the September 8 Council meeting.

Q&A Document

September 8, 2026

City Council Voting Session

The City of Prescott has awarded a Construction Manager at Risk (CMAR) Guaranteed Maximum Price (GMP) contract to Fann Contracting, Inc. for pre-construction services. Fann Contracting, a Prescott-based contractor, was selected through a competitive qualification-based process earlier this summer.

CMAR is a project delivery method that brings a construction firm onto the project during design to assist the engineering firm and city bridge the gap between design and construction, providing market-driven estimating and value engineering opportunities.  The CMAR will act as a key consultant during the design phase to assist in optimizing budgets, schedules, and constructability.

The project is approaching 60% design completion. Stay tuned for more information.